| Rebuilding of Greens - Week of May 28th, 2007
| Bunker Drainage installation #11 and #4 bunkers. Each green side bunker that is rebuilt will have drainage installed. |

 |
| #4 bunker red line indicates where new grass line will be. Sand faces on all the green side bunkers are being reduced to help reduce plug lies and improve playability. |
 |
| #4 and #5 green drainage installation |


|
| New design of # 9 green side bunkers. Up to nine feet of sand face has been reduced on the right side bunker. |



 |
| #1 green side bunker |

 |
| #15 green side bunkers |

 |
|
|
|