| Granite is being installed in the greens. Greens 9- 18 have been completed. |




|
| Root zone mix is being installed to the grens. Greens 10-17 haver been completed. |


 |
| The root zone mix is carefully applied at a 12 inch depth and much care is taken not to disturb or damage the granite layer (Video) |
|
| A motorized plate compactor is used to firm all areas of the green. This machine is called a jumping jack for obvious reasons.(Video) |
|
| We have started to fumigate greens. Greens 10-15 have been completed. |


 |
| We are working to remove debris and logs from the berms left of holes 4 and 5. |


 |
|
|